Renovation Consulting & Initial Property Assessment Inspectors for Residential Housing

  • Homeowner and Contractor to meet before the confirmed Draw Inspection appointment
  • Homeowner and Contractor to go over the blank Draw Request forms (sent by the Front Office when making the appointment)
  • Homeowner and Contractor to review and discuss together
  • If permits are required, Contractor needs to have a copy ready and available to give at the First Draw Inspection on site to the Consultant
  • CHANGE ORDER
    • items requested by the Contractor must be written on their company letter head
    • any applicable receipts needs to be sent with the company letter head
    • Contractor’s invoices need to have the name of the client and property address
    • Send documents to the Consultant’s email address for review
    • NO WORK WILL BE DONE WITHOUT APPROVAL FROM THE LENDER
    • $100 Change Order Fee (for each Change Order)
    • Homeowner is responsible for Change Order fee if lender does not pay
    • Work outside "Scope of Work" or SOR, homeowner is responsible to pay the Contractor
  • The Borrower and Contractor must provide final inspections for any work for which applicable permits were required.
  • Any disputes between the Borrower and Contractor must be resolved by the Borrower and Contractor in accordance with the provisions of the Homeowner/Contractor Agreement.

Our Commitment

We Do 4 Things 1 Way
  1. Provide Great Service
  2. At a Fair Price
  3. Accurately Performed
  4. Promptly Delivered

The 1 way: 

With Honor to Our Customers and to Their Customers